| Sr. No. |
Key Acceptance Criteria |
Dimension |
Standard |
Method |
Note |
Observation |
Outcome |
Uploads |
| (Level 1) Valve |
| (Level 2) Design Doc |
| (Level 3) Raw Material |
| 1 |
Purchase Order |
|
|
Review |
Yes / No; PO Number |
Yes PO available |
Accept
|
|
| 2 |
Project Referece |
|
|
Review |
Yes / No; PO Number |
Petrofac-LNG |
Accept
|
|
| 3 |
Material Requisition (MR) |
|
|
Review |
Yes / No; Doc No |
MR available |
Accept
|
|
| 4 |
Inspection Test Plan (ITP) |
|
|
Review |
Yes / No; Approved vs Not Approved; Doc No |
ITP available |
Accept
|
|
| 5 |
Drawing |
|
|
Review |
Yes / No; Approved vs Not Approved; Doc No |
Drg reviewed |
Accept
|
|
| 6 |
Technical Specification |
|
|
Review |
Yes / No; Doc No |
TS reviewed |
Accept
|
|
| 7 |
Data Sheets |
|
|
Review |
Yes / No; Approved vs Not Approved; Doc No |
Supplier data sheet reviewed |
Accept
|
|
| 8 |
Procedures |
|
|
Review |
Yes / No; Approved vs Not Approved; Doc No |
OK |
Accept
|
|
| 9 |
Inspection Call |
|
|
Review |
Yes /No; Doc no |
|
|
|
| 10 |
Offer List |
|
|
Review |
Yes / No; Doc no |
OK |
Accept
|
|
|
| Final Observation | CAPA |
OK |
Accept
|